IV. Contract Authorization - Sante Fe Storm-water Damage
a. Staff request City Council authorize a contract for construction with American Civil
Constructors Inc. for the Santa Fe storm water damage. Staff: Public Works Director
Maria D' Andrea
Emergency Purchase Authorization-Santa Fe Stormwater System Damage - Pdf
V. Adjournment
Page 1 of 6
COUNCIL COMMUNICATION
TO: Mayor and Council
FROM: Maria DAndrea
DEPARTMENT: Public Works
DATE: August 15, 2019
SUBJECT:
Emergency Purchase Authorization-Santa Fe Stormwater System
Damage
DESCRIPTION:
Emergency Purchase Authorization-Santa Fe Stormwater System Damage
RECOMMENDATION:
Staff requests Council approve an agreement with American Civil Constructors, Inc., for the
continuation of the emergency repairs upon the stormwater sewer underlying Oxford in an
amount not to exceed $280,000, such amount in addition to those funds previously authorized
pursuant to Emergency Purchase Resolution #57, Series of 2019, as approved on July 3rd,
2019, and amended on July 11, 2019.
PREVIOUS COUNCIL ACTION:
Resolution #57, Series of 2019, dated July 3, 2019 approved an emergency purchase order with
American Civil Constructors, Inc. for emergency repairs to the stormwater system underlying
Oxford and the surrounding area, following the failure of the pipe resulting in a sinkhole, all
arising out of a rain storm occurring on July 1, 2019. The original resolution of emergency
purchase authorized repairs in an amount not to exceed $120,000. On July 11, 2019 Council
amended that Resolution and authorized an additional expenditure of $120,000 for a total
amount not to exceed $240,000.
The administrative procurement grid approved by the City Council through Resolution #14,
Series of 2019, dated April 1, 2019, requires the Mayor or Mayor Pro Tem to call a Special
Meeting of the City Council to authorize emergency expenditures in excess of $100,000.
SUMMARY:
The previous Director of Utilities procured American Civil Constructors (ACC) to begin repairs to
the damaged storm sewer. That work began on July 2, 2019. American Civil Constructors was
selected to provide the emergency services as they had completed previous work on another
section of that stormwater pipe following a previous sinkhole event. ACC immediately began
work to secure the area and render the area safe for the community. Next, with the assistance
of City staff, ACC began an in-depth investigation and inspection of the area in which the failure
occurred. ACC discovered that an additional 110 feet of storm sewer pipe was unstable and
required immediate replacement. As work progressed, the contractor encountered a large (48"
diameter) sanitary sewer main running perpendicular to Oxford Street that crosses over the
storm sewer line being replaced. While the sanitary sewer main was marked, the depth of the
main in proximity to the depth of the storm sewer was previously unknown. As the contractor
excavated the storm sewer pipe, it was determined that removing the storm sewer and replacing
Page 2 of 6
it poses a serious risk to the reliability of the sanitary sewer pipe, potentially resulting in that
pipe’s failure. There are also several other utility crossings which will need to be shored or
braced, as well as repairing/replacing the remainder of the pipe replacement. To protect the
sanitary sewer line engineers are proposing soil stabilization to hold up the sanitary sewer line
using a specialized contractor. Several other utilities along the remainder of the storm sewer line
that will be replaced will also require soil stabilization or shoring.
Work upon the emergency repairs has been stopped until a solution could be determined, and
action approved by the City Council.
Of the $240,000 authorized to date, approximately $220,000 has been expended, but work is
still needed to complete the repair. Staff estimates remaining repairs to the stormwater pipe
itself will cost the City an additional $80,000 to complete. So, an additional allocation of $90,000
is being requested for this purpose. ($110,000 to complete, less $20,000 remaining authorized
funds = $60,000)
Two quotes were solicited for the soil stabilization work. The low bid was just over $120,000.
Finally, a spot repair to remove the section of pipe and concrete that was washed downstream
and lodged in the pipe as shown to the City Council on July 12, 2019, is estimated to cost
$25,000. With markups (estimated at $20,000) by the contractor, the total additional cost is
estimated to be $280,000.
There are also additional costs related to paving the enlarged excavation site anticipated to be
$55,000. The city's Mill & Overlay contractor is providing a quote to complete this work as a
change order to their contract.
FINANCIAL IMPLICATIONS:
Of the $240,000 authorized to date, approximately $220,000 has been expended. These are
detailed by ACC based on the time & materials expended as well as rental costs for shoring
equipment, etc.
Funds for the expenditure will come from the storm drainage fund which currently has an
available balance of $773,531. Should the entire additional $280,000 be used, the remaining
available balance would be $493,531.
Initial Authorization $120,000
Second Authorization $120,000
Current Authorization $280,000
Total Estimated Cost $520,000
ALTERNATIVES:
The alternative to immediately addressing these newly discovered stormwater system issues is
to delay the necessary repairs, leaving the emergency project incomplete. Completion of this
emergency project could be incorporated into the proposed comprehensive storm sewer system
improvements. Staff does not recommend this alternative because the high risk of failure in this
section of stormwater pipe poses a danger to the safety of the community.
CONCLUSION:
Page 3 of 6
Staff requests the City Council authorize the additional expenditure of up to $280,000 for a total
project authorization in an amount not to exceed $520,000, all directly arising out of the
emergency repairs to the stormwater system and surrounding area caused by the pipe failure
from the July 1, 2019 rain storm.
ATTACHMENTS:
Contract Approval Summary
Page 4 of 6
Contract Approval Summary
V10/25/2017
Page | 1
Contact Identification Information (to be completed by the City Clerk)
ID number: Authorizing Resolution/Ordinance:
Recording Information:
City Contact Information
Staff Contact Person: Maria D'Andrea Phone: 303-762-2506
Title: Director of Public Works Email:
mdandrea@englewoodco.gov
Vendor Contact Information
Vendor Name: American Civil Constructors,
LLC
Vendor Contact:
Vendor Address:4901 S Windermere St Vendor Phone: 303-795-2582
City: Littleton Vendor Email:
State: CO Zip Code: 80120
Contract Type
Contract Type:Construction Agreement
Description of ‘Other’ Contract Type:
Description of Contract Work/Services:
Attachments:
☒Contract -- ☐Original ☐Copy
☐Addendum(s)
☐Exhibit(s)
☐Certificate of Insurance
Summary of Terms:
Start Date: 07/01/2019 End Date: 09/30/2019 Total Years of Term: 1
Total Amount of Contract for term (or estimated amount
if based on item pricing):
$120,000.00
If Amended: Original Amount
$120,000
Amendment Amount
$400,000
Total as Amended:
$520,000.00
Renewal options available:
N/A
Payment terms (please
describe terms or attach
schedule if based on
deliverables):
Upon completion of work
Attachments:
☐Copy of original Contract if this is an amendment
Repair of storm sewer pipe in Oxford Avenue & surrounding area
Page 5 of 6
Contract Approval Summary
V10/25/2017
Page | 2
☐Copies of related Contracts/Conveyances/Documents
Source of funds (Insert Excel Document Image):
Attachment (For Capital Items Only / Expense Line Item Detail is Located in Open Gov):
☐Prior Month-End Project Status and Fund Balance Report
Process for Choosing Vendor:
☐Bid: ☐ Bid Evaluation Summary attached
☐ Bid Response of proposed awardee
☐RFP: ☐ RFP Evaluation Summary attached
☐ RFP Response of proposed awardee
☐Quotes: Copy of Quotes attached
☒Sole Source: Explain Need below
☐Other: Please describe
CAPITAL ONLY A B C 1 = A-B-C
Capital
Operating Year
Tyler / New
World
Project # / Task#Fund Division Object
Line Item
Description Budget Spent to Date
Contract
Amount
Budget
Remaining
Capital 2019 34 1101 003
Technology &
Equipment 773,531.00$ -$ 280,000.00$ 493,531.00$
-$
Total by Fund and Current Year 773,531.00$ -$ 280,000.00$ 493,531.00$
C 2020 -$ -$ -$ -$
O 2020 -$ -$ -$ -$
Total by Fund and Next Year -$ -$ -$ -$
Grand Total 773,531.00$ -$ 280,000.00$ 493,531.00$
NOTES (if needed): For Operating Expense Line Item Detail, please review information provided in OpenGov. For Capital items, please review
Attachment - Prior Month Project Status and Fund Balance Report
CAPITAL & OPERATING EXPENSE
Emergency repair. ACC is located near the repair site and is able to mobilize the
necessary equipment and resources to complete the work in a timely manner
Page 6 of 6